The La Virgen Valley Production Camp currently encompasses two high grade operating silver mines, Chivo Mine - Largest & Highest Silver Grade Mine in the district and the San Ramon Mine - High Lead & Zinc Grade. Ore is transported to the 500 tpd processing plant in the Guadalupe mining camp for processing which currently operates at 343 tonnes per day (tpd).
PRODUCTION
Year Ended |
6 Months Ended June 30th 2010 |
Dec 31st 2009 |
Dec 31st 2008 |
Dec 31st 2007 |
Change |
| Silver Production (oz) |
360,767 |
823,571 |
645,668 |
348,949 |
+82% |
| Lead (t) |
380 |
969 |
813 |
601 |
+35% |
| Zinc (t) |
521 |
1,098 |
1,053 |
976 |
+8% |
| Revenue per production tonne sold |
$104.46 |
$109.51 |
$89.89 |
$72.56 |
+24% |
| CA$ direct cost/tonne produced |
$54.25 |
$60.39 |
$54.80 |
$44.15 |
+24% |
Chivo Mine
Chivo is the largest and highest grade producing mine in the district. It is the second mine put into production by the Company's team. Chivo was identified as a high priority exploration target in late 2005 when sampling in an old small mine working and on surface returned high grade values of 1,095g/t Silver over 1.25m TW and 2,640 g/t Silver over 0.85m TW respectively. In 2006, IMPACT began drilling and by 2008 had completed 46 drill holes outlining the high grade Chivo Silver Shoot over an area of 300m long and 200m deep. Commercial mining began in January 2008. The zone remains open for expansion in all directions. Currently, Chivo provides the majority of the production.
Recent drilling results from Chivo included the following:
| CHIVO DRILL HOLES (MAIN VEIN - SOUTH EXTENSION) |
DRILL HOLE No. |
TOP OF INTERCEPT (m) |
ESTIMATED TRUE WIDTH (m) |
SILVER (g/t) |
SILVER (oz/ton) |
GOLD (g/t) |
ZINC (%) |
LEAD (%) |
| SECTION 850N (Drill holes listed from west to east) |
| Z08-13 |
49.4 |
1.9 |
3,902 |
114 |
1.34 |
3.96 |
2.16 |
| Including |
0.6 |
11,463 |
334 |
3.46 |
10.25 |
5.02 |
| Z08-14 |
65.4 |
0.7 |
601 |
18 |
0.22 |
1.74 |
1.56 |
| SECTION 875N (Drill holes listed from west to east) |
| Z08-25 |
45.6 |
3.2 |
865 |
25 |
0.41 |
3.73 |
3.90 |
| Including |
1.6 |
1,765 |
51 |
0.81 |
6.42 |
7.56 |
| Z08-11 |
58.4 |
3.2 |
793 |
23 |
0.21 |
4.23 |
3.27 |
| Including |
1.1 |
1,792 |
52 |
0.46 |
8.73 |
7.25 |
| Z08-12 |
71.3 |
1.7 |
91 |
3 |
0.86 |
2.03 |
2.65 |
| SECTION 900N (Drill holes listed from west to east) |
| Z08-16 |
57.7 |
1.6 |
664 |
19 |
0.79 |
3.23 |
1.79 |
| Z08-23 |
76.6 |
3.0 |
501 |
15 |
0.51 |
8.51 |
4.96 |
| Including |
1.8 |
810 |
24 |
0.80 |
12.75 |
6.91 |
| Z08-24 |
88.0 |
1.3 |
73 |
2 |
0.66 |
10.96 |
2.81 |
| Z08-27 |
114.5 |
3.7 |
89 |
3 |
0.22 |
6.91 |
2.81 |
| Including |
1.1 |
175 |
5 |
0.60 |
14.95 |
6.91 |
San Ramon Mine
San Ramon is located 1.3 km south of the Chivo Mine and supplements production from Chivo The main mineral shoot is typically 60m long by 3m wide and hosts high grade silver ores.
Mining continues to expand at San Ramon as the Company also developed underground access to a parallel structure, the Chaparrita Vein. During the third quarter of 2009, a new wide zone of silver-rich stockwork breccia style mineralization was discovered on level 5.5 and is expected to increase production at the mine.
At San Ramon two drill programs have taken place mainly prior to intial production. The holes were drilled to both determine the size of the San Ramon Mine and to plan for future mining. The most significant results returned from both programs include the following:
Drill Hole |
Top of
Intercept (m) |
Est. True
Width (m) |
Silver
(g/t) |
Silver (oz/t |
Gold (g/t) |
Zinc (%) |
Lead (%) |
1 |
243.6 |
0.9 |
279 |
8.1 |
0.11 |
2.52 |
1.47 |
|
including |
0.2 |
957 |
27.9 |
0.04 |
2.66 |
1.02 |
4 |
133.8 |
0.9 |
746 |
21.8 |
0.36 |
3.08 |
1.08 |
Concepcion Vein
Drill Hole |
Top of
Intercept (m) |
Est. True
Width (m) |
Silver
(g/t) |
Silver (oz/t) |
Gold (g/t) |
Zinc (%) |
Lead (%) |
1 |
138.8 |
1.8 |
293 |
10.46 |
0.4 |
1.25 |
1.4 |
2 |
163.5 |
0.8 |
6,013 |
214.8 |
2.31 |
0.36 |
0.47 |
3 |
127.8 |
0.4 |
115 |
4.1 |
0.29 |
3.67 |
1.05 |
4 |
153.6 |
4.4 |
2,713 |
96.9 |
0.36 |
1.01 |
0.74 |
Including: |
|
0.4 |
27,793 |
992.6 |
3.4 |
9.47 |
7.52 |
San Agustin Vein
Drill Hole |
Top of Intercept (m) |
Est. True Width (m) |
Silver
(g/t) |
Silver (oz/t) |
Gold (g/t) |
Zinc (%) |
Lead (%) |
2 |
174.2 |
1.6 |
3,234 |
115.5 |
0.41 |
2.67 |
1.91 |
Including: |
163.5 |
0.7 |
7,010 |
250.4 |
0.73 |
5.87 |
4.26 |
3 |
127.8 |
1.2 |
450 |
16.1 |
0.23 |
2.3 |
0.75 |
4 |
153.6 |
0.6 |
1,140 |
40.7 |
0.56 |
0.56 |
0.23 |
EXPLORATION
Cometa Navideno/Santiago Vein
Earlier sampling of the historic Santiago mine workings by IMPACT returned average values of 235g/t silver and 0.31g/t gold across 0.9m (TW) ranging up to a high of 1,320g/t silver and 0.99g/t gold across 0.3m (TW). Earlier results from this Shoot reported a median value of 680g/t Ag and 0.3g/t Au over 0.90m to a high of 1,128g/t Ag and 0.2g/t Au over 1.9m. Two holes were drilled here in 2005. One of the holes returned 7.26% zinc, 7.45% lead, 75g/t silver and 0.59g/t Au across 0.65m about 120m below the old mine workings.
Los Reyes Zone
Finding other clusters of large veins situated next to a producing mine allows IMPACT to readily and quickly integrate them into production. An example is the Los Reyes Zone, located 600 metres east of the Chivo Mine. It is a thick vein system that trends parallel to the silver-rich Chivo Zone. Highlights from an 11-hole drill program include the following:
| LOS REYES DRILL HOLES (MAIN VEIN) |
DRILL HOLE
No. |
TOP OF
INTERCEPT (m) |
ESTIMATED
TRUE WIDTH (m) |
SILVER
(g/t) |
GOLD
(g/t) |
ZINC
(%) |
LEAD
(%) |
SECTION 1N (Sections listed from south to north, drill holes listed from west to east) |
| Z07-42 |
111.2 |
4.5 |
262 |
0.09 |
2.05 |
0.64 |
| Including |
2.2 |
496 |
0.15 |
3.10 |
0.96 |
| Including |
1.1 |
717 |
0.27 |
1.67 |
0.44 |
| Z06-33 |
115.1 |
5.2 |
17 |
0.18 |
1.64 |
0.55 |
| SECTION 2N |
| Z07-35 |
194.9 |
1.1 |
25 |
2.21 |
4.35 |
1.28 |
| SECTION 3N |
| Z07-37 |
191.1 |
4.1 |
46 |
0.34 |
4.46 |
1.07 |
| Including |
0.6 |
135 |
1.24 |
17.80 |
4.62 |
| SECTION 3N |
| Z07-38 |
202.4 |
5.9 |
22 |
0.18 |
1.99 |
0.53 |
The Company's mine staff will evaluate the Los Reyes Zone for possible integration into the Chivo Mine Plans.
News Releases
| July 27, 2010 |
Impact Silver Announces First Results From 5,000M Drill Program At Zacualpan Silver District |
San Ramon:
Chivo:
| August 12, 2008 |
Impact Drills 11,463g/t (334 oz/ton) Silver Over 0.6M (2ft) At Chivo Mine And Expands Strike Length By 40% |
| August 06, 2008 |
Impact Drills 1,118 G/T Silver Across 1.4 Meters At The Chivo Mine |
| June 17, 2008 |
Impact Silver Updates Production And Samples 657G/T Silver Over 2.85M At The Chivo Mine |
| April 24, 2008 |
Impact Silver Extends Strike Length Of Chivo Mine; Drills 12.3 Meters Of 6% Zinc And 2% Lead |
| September 20, 2007 |
Impact Silver Corp. Commences Construction Of Third Mine And Increases Production |
| July 12, 2007 |
Impact Silver Announces Chivo Drill Results |
| October 12, 2006 |
Impact Discovers New High Grade Silver Shoot |
| April 27, 2006 |
IMPACT Silver Announces Signing of Drill Contract |
| September 07, 2005 |
New High Grade Silver Discoveries |
Los Reyes:
| April 29, 2008 |
Impact Silver Announces New Discovery At The Royal Mines Of Zacualpan |
San Antonio:
| August 28, 2008 |
Impact Silver Acquires New Concessions Increasing Mineral Holdings By 45% |
San Augustin, Cometa Navideno, Santiago, Concepcion:
Maps & Images
|
 |
|
 |